Call us Today :
+213 672 627004
Email :
contact@scs-atm.com
Qualified
PROFESSIONALS
ISO CERTIFICATION
ISO 9001 / 14001 / 45001 / 29001
Home
Services
Mechanical completion of non-operational systems
HVAC
Safety
Surface protection, Insulation and Fire proofing
Electrical
Piping
Typical commissioning preparation activities
Structural
Mechanical
Architectural
Instrument & Telecommunication
Company
About Us
Cooperation & Clients
Contact
Previous
Next
Typical completion activities
Instrument/Telecommunication
Calibration and testing of instruments prior to installation.
Visual inspection for complete and correct installation.
Insulation and continuity testing of cables.
Cleaning, flushing, pressure and leak testing of pneumatic and hydraulic tubing.
Adjustment of control, alarm and shutdown settings.
Loop testing.
Function testing of control systems.
Function testing of field instruments.
Hot oil flushing of instrument tubing.
Preservation.